| Index | Recent Threads | Unanswered Threads | Who's Active | Guidelines | Search |
| World Community Grid Forums
|
| No member browsing this thread |
|
Thread Status: Active Total posts in this thread: 957
|
|
| Author |
|
|
Sgt.Joe
Ace Cruncher USA Joined: Jul 4, 2006 Post Count: 7846 Status: Offline Project Badges:
|
I have recently learned the following information from WCG and still believe there is no calculable end date. However I will still attempt to track the progress as it occurs. A big thanks to the WCG staff for making this available. I have decided to leave the original quote in for the time being as it still addresses the question of additional work.
----------------------------------------Recently another estimated 5,000 batches were added to the project. We are not able to say the exact number of additional batches that will be added in the future, but we are fully expecting to receive more work units for the Mapping Cancer Markers project. The researchers will turn to other cancer-type work units when the current ones near completion. Last 30 day average results:463,092Percentage Complete:Currently listed on the Research page:57%. I have adjusted my figures to an estimated total of 70,500 batches currently.(Little tweak) The average length of a WU is currently running about 4.18 hours, slightly shorter than the last time I posted, but continuing to trend steady at around the 4 to 4.3 hour mark consistently. The average length of a work unit this past week varied between 4.17 and 4.30 hours. This continues to be remarkably steady. Still have not seen any of the batches from 122278 to 122402. The ovarian units started with 122403 as the lowest number.My latest batch number was 140440 which would give about 154 batches for the week. The batch count for last week was 172. Production increased this past week going from about 3.08 million WU's to 3.09 million WU's completed. During this past week the time devoted to MCM1 was just slightly over an average of 212 years per day, up slightly from the past week's 211. Originally we had 17,500 batches. My current estimate for the number of batches is 70,500. I have virtually given up trying to track the changes as to when the researchers are adding them. As of today(February 25) we have done 808,996,502 units. This would be about 57.37% of the known work units. The percentage on the Research page (57%)has been fluctuating up and down, which probably reflects the injection of new batches by the scientists, or the slowdown in the amount done by the project. If I get too far out of whack I will re-assess my numbers. Based on the 30 day running average the current work units should last to about September of 2021, about the same as last week. When looking this far into the future the crystal ball gets very hazy. This not an end of project projection, just a projection of a probable end of the current (maybe) known work units. I am trying to calculate a couple of different ways to try to get some figures which converge to about the same. At any rate, there should be about 3.5 years left to crunch on this project at the present rate. I have revised the second graph to reflect the change in total work units as of July 16, 2017.This should be a better representation of the potential end of the project, given the present parameters. Cheers
Sgt. Joe
*Minnesota Crunchers* |
||
|
|
[SG-FC]Hammerburg
Senior Cruncher Joined: Apr 26, 2007 Post Count: 251 Status: Offline Project Badges:
|
And again thank you for your Update Sgt. Joe!
----------------------------------------![]() |
||
|
|
Sgt.Joe
Ace Cruncher USA Joined: Jul 4, 2006 Post Count: 7846 Status: Offline Project Badges:
|
I have recently learned the following information from WCG and still believe there is no calculable end date. However I will still attempt to track the progress as it occurs. A big thanks to the WCG staff for making this available. I have decided to leave the original quote in for the time being as it still addresses the question of additional work.
----------------------------------------Recently another estimated 5,000 batches were added to the project. We are not able to say the exact number of additional batches that will be added in the future, but we are fully expecting to receive more work units for the Mapping Cancer Markers project. The researchers will turn to other cancer-type work units when the current ones near completion. Last 30 day average results:462,647Percentage Complete:Currently listed on the Research page:57%. I have adjusted my figures to an estimated total of 70,500 batches currently.(Little tweak) The average length of a WU is currently running about 4.11 hours, slightly shorter than the last time I posted, but continuing to trend steady at around the 4 to 4.3 hour mark consistently. The average length of a work unit this past week varied between 4.10 and 4.17 hours. This continues to be remarkably steady. Still have not seen any of the batches from 122278 to 122402. The ovarian units started with 122403 as the lowest number.My latest batch number was 140620 which would give about 180 batches for the week. The batch count for last week was 154. Production increased this past week going from about 3.09 million WU's to 3.16 million WU's completed. During this past week the time devoted to MCM1 was just slightly over an average of 212.7 years per day, up slightly from the past week's 212.4. Originally we had 17,500 batches. My current estimate for the number of batches is 70,500. I have virtually given up trying to track the changes as to when the researchers are adding them. As of today(March 4) we have done 812,165,248 units. This would be about 57.6% of the known work units. The percentage on the Research page (57%)has been fluctuating up and down, which probably reflects the injection of new batches by the scientists, or the slowdown in the amount done by the project. (On March 9,2018 it moved to 58%)If I get too far out of whack I will re-assess my numbers. Based on the 30 day running average the current work units should last to about August/September of 2021, about the same as last week. When looking this far into the future the crystal ball gets very hazy. This not an end of project projection, just a projection of a probable end of the current (maybe) known work units. I am trying to calculate a couple of different ways to try to get some figures which converge to about the same. At any rate, there should be about 3.5 years left to crunch on this project at the present rate. I have revised the second graph to reflect the change in total work units as of July 16, 2017.This should be a better representation of the potential end of the project, given the present parameters. Cheers
Sgt. Joe
*Minnesota Crunchers* |
||
|
|
Dayle Diamond
Senior Cruncher Joined: Jan 31, 2013 Post Count: 452 Status: Offline Project Badges:
|
Thank you so much for your diligence with this post, Sgt. Joe.
|
||
|
|
Sgt.Joe
Ace Cruncher USA Joined: Jul 4, 2006 Post Count: 7846 Status: Offline Project Badges:
|
I have recently learned the following information from WCG and still believe there is no calculable end date. However I will still attempt to track the progress as it occurs. A big thanks to the WCG staff for making this available. I have decided to leave the original quote in for the time being as it still addresses the question of additional work.
----------------------------------------Recently another estimated 5,000 batches were added to the project. We are not able to say the exact number of additional batches that will be added in the future, but we are fully expecting to receive more work units for the Mapping Cancer Markers project. The researchers will turn to other cancer-type work units when the current ones near completion. Last 30 day average results:466,773Percentage Complete:Currently listed on the Research page:58%. I have adjusted my figures to an estimated total of 70,500 batches currently.(Little tweak) The average length of a WU is currently running about 4.17 hours, slightly longer than the last time I posted, but continuing to trend steady at around the 4 to 4.3 hour mark consistently. The average length of a work unit this past week varied between 4.13 and 4.21 hours. This continues to be remarkably steady. Still have not seen any of the batches from 122278 to 122402. The ovarian units started with 122403 as the lowest number.My latest batch number was 140827 which would give about 207 batches for the week. The batch count for last week was 180. Production increased this past week going from about 3.16 million WU's to 3.34 million WU's completed. During this past week the time devoted to MCM1 was just slightly over an average of 227 years per day, up slightly from the past week's 212.7. Originally we had 17,500 batches. My current estimate for the number of batches is 70,500. I have virtually given up trying to track the changes as to when the researchers are adding them. As of today(March 11) we have done 815,505,413 units. This would be about 57.9% of the known work units. The percentage on the Research page (58%)has been fluctuating up and down, which probably reflects the injection of new batches by the scientists, or the slowdown in the amount done by the project. (On March 17,2018 it moved to 59%)If I get too far out of whack I will re-assess my numbers. Based on the 30 day running average the current work units should last to about August/September of 2021, about the same as last week. When looking this far into the future the crystal ball gets very hazy. This not an end of project projection, just a projection of a probable end of the current (maybe) known work units. I am trying to calculate a couple of different ways to try to get some figures which converge to about the same. At any rate, there should be about 3.5 years left to crunch on this project at the present rate. I have revised the second graph to reflect the change in total work units as of July 16, 2017.This should be a better representation of the potential end of the project, given the present parameters. Cheers
Sgt. Joe
----------------------------------------*Minnesota Crunchers* [Edit 1 times, last edit by Sgt.Joe at Mar 17, 2018 2:41:11 PM] |
||
|
|
[SG-FC]Hammerburg
Senior Cruncher Joined: Apr 26, 2007 Post Count: 251 Status: Offline Project Badges:
|
And again thank you for your Update Sgt. Joe!
----------------------------------------![]() |
||
|
|
Sgt.Joe
Ace Cruncher USA Joined: Jul 4, 2006 Post Count: 7846 Status: Offline Project Badges:
|
I have recently learned the following information from WCG and still believe there is no calculable end date. However I will still attempt to track the progress as it occurs. A big thanks to the WCG staff for making this available. I have decided to leave the original quote in for the time being as it still addresses the question of additional work.
----------------------------------------Recently another estimated 5,000 batches were added to the project. We are not able to say the exact number of additional batches that will be added in the future, but we are fully expecting to receive more work units for the Mapping Cancer Markers project. The researchers will turn to other cancer-type work units when the current ones near completion. Last 30 day average results:474,597Percentage Complete:Currently listed on the Research page:59%. I have adjusted my figures to an estimated total of 70,500 batches currently.(Little tweak) The average length of a WU is currently running about 4.05 hours, slightly shorter than the last time I posted, but continuing to trend steady at around the 4 to 4.3 hour mark consistently. The average length of a work unit this past week varied between 4.05 and 4.22 hours. This continues to be remarkably steady. Still have not seen any of the batches from 122278 to 122402. The ovarian units started with 122403 as the lowest number.My latest batch number was 140909 which would give about 152 batches for the week. The batch count for last week was 207. Production increased this past week going from about 3.34 million WU's to 3.37 million WU's completed. During this past week the time devoted to MCM1 was just slightly over an average of 227.7 years per day, up slightly from the past week's 227.3. Originally we had 17,500 batches. My current estimate for the number of batches is 70,500. I have virtually given up trying to track the changes as to when the researchers are adding them. As of today(March 18) we have done 818,871,685 units. This would be about 58.1% of the known work units. The percentage on the Research page (59%)has been fluctuating up and down, which probably reflects the injection of new batches by the scientists, or the slowdown in the amount done by the project. If I get too far out of whack I will re-assess my numbers. Based on the 30 day running average the current work units should last to about August/September of 2021, about the same as last week. When looking this far into the future the crystal ball gets very hazy. This not an end of project projection, just a projection of a probable end of the current (maybe) known work units. I am trying to calculate a couple of different ways to try to get some figures which converge to about the same. At any rate, there should be about 3.4 years left to crunch on this project at the present rate. I have revised the second graph to reflect the change in total work units as of July 16, 2017.This should be a better representation of the potential end of the project, given the present parameters. Cheers
Sgt. Joe
*Minnesota Crunchers* |
||
|
|
Sgt.Joe
Ace Cruncher USA Joined: Jul 4, 2006 Post Count: 7846 Status: Offline Project Badges:
|
I have recently learned the following information from WCG and still believe there is no calculable end date. However I will still attempt to track the progress as it occurs. A big thanks to Erika T. for making a new quote available.
----------------------------------------There is no projected end date for this project at this time. The progress bar on the Research Page is an estimate given the current number of work units available. More work units will be added over time, which will change the date and percentage shown on the progress bar. Last 30 day average results:453,409As has been discussed in various forum threads, we are looking to change these progress bars in the near future. Thank you for your support, ErikaT Percentage Complete:Currently listed on the Research page:57%. I have adjusted my figures to an estimated total of 71,500 batches currently.(Little tweak, up 1000 from the last update.) The average length of a WU is currently running about 4.22 hours, slightly longer than the last time I posted, but continuing to trend steady at around the 4 to 4.3 hour mark consistently. The average length of a work unit this past week varied between 4.21 and 4.30 hours. This continues to be remarkably steady. Still have not seen any of the batches from 122278 to 122402. The ovarian units started with 122403 as the lowest number.My latest batch number was 141347 which would give about 149 batches for the week. The batch count for last week was 113. Production decreased this past week going from about 2.87 million WU's to 2.56 million WU's completed. During this past week the time devoted to MCM1 was just slightly over an average of 178 years per day, down slightly from the past week's 196. Originally we had 17,500 batches. My current estimate for the number of batches is 71,500. I have virtually given up trying to track the changes as to when the researchers are adding them. As of today(April 8) we have done 827,658,132 units. This would be about 57.8% of the known work units. The percentage on the Research page (57%)has been fluctuating up and down, which probably reflects the injection of new batches by the scientists, or the slowdown in the amount done by the project. If I get too far out of whack I will re-assess my numbers, which I did this week. Based on the 30 day running average the current work units should last to about October of 2021, a slippage of about a month. When looking this far into the future the crystal ball gets very hazy. This not an end of project projection, just a projection of a probable end of the current (maybe) known work units. I am trying to calculate a couple of different ways to try to get some figures which converge to about the same. At any rate, there should be about 3.5 years left to crunch on this project at the present rate. I have revised the second graph to reflect the change in total work units as of April 8, 2017.This should be a better representation of the potential end of the project, given the present parameters. I took a couple of weeks off of updating the project, but I will try to keep it to a weekly update if I can. Thanks for your patience. Cheers
Sgt. Joe
*Minnesota Crunchers* |
||
|
|
Sgt.Joe
Ace Cruncher USA Joined: Jul 4, 2006 Post Count: 7846 Status: Offline Project Badges:
|
I have recently learned the following information from WCG and still believe there is no calculable end date. However I will still attempt to track the progress as it occurs. A big thanks to Erika T. for making a new quote available.
----------------------------------------There is no projected end date for this project at this time. The progress bar on the Research Page is an estimate given the current number of work units available. More work units will be added over time, which will change the date and percentage shown on the progress bar.As has been discussed in various forum threads, we are looking to change these progress bars in the near future. Last 30 day average results:416,187Thank you for your support, ErikaT Percentage Complete:Currently listed on the Research page:56%. I have adjusted my figures to an estimated total of 74,500 batches currently.(Little tweak, up 2500 from the last update.) The average length of a WU is currently running about 4.17 hours, slightly shorter than the last time I posted, but continuing to trend steady at around the 4 to 4.3 hour mark consistently. The average length of a work unit this past week varied between 4.06 and 4.26 hours. This continues to be remarkably steady. Still have not seen any of the batches from 122278 to 122402. The ovarian units started with 122403 as the lowest number.My latest batch number was 141654 which would give about 119 batches for the week. The batch count for last week was 188. Production increased this past week going from about 2.7 million WU's to 2.96 million WU's completed. During this past week the time devoted to MCM1 was just slightly over an average of 200 years per day, up slightly from the past week's 186. Originally we had 17,500 batches. My current estimate for the number of batches is 74,000. I have virtually given up trying to track the changes as to when the researchers are adding them. As of today(April 22) we have done 827,658,132 units. This would be about 57.8% of the known work units. The percentage on the Research page (57%)has been fluctuating up and down, which probably reflects the injection of new batches by the scientists, or the slowdown in the amount done by the project. If I get too far out of whack I will re-assess my numbers, which I did this week. Based on the 30 day running average the current work units should last to about May-June of 2022, a slippage of about six months. When looking this far into the future the crystal ball gets very hazy. This not an end of project projection, just a projection of a probable end of the current (maybe) known work units. I am trying to calculate a couple of different ways to try to get some figures which converge to about the same. At any rate, there should be about 4 years left to crunch on this project at the present rate. I have revised the second graph to reflect the change in total work units as of April 22, 2017.This should be a better representation of the potential end of the project, given the present parameters. I took a couple of weeks off of updating the project, but I will try to keep it to a weekly update if I can. Thanks for your patience. Cheers
Sgt. Joe
*Minnesota Crunchers* |
||
|
|
PabloMalaga
Advanced Cruncher Joined: Jul 7, 2011 Post Count: 51 Status: Offline Project Badges:
|
Do you know when the ovarian work units end and the next type of cancer begins?
May / June 2022 is when the ovarian work units end? |
||
|
|
|