Hello,
Quick problem...
I have data correctly coming from MIB as the value '1' and this is being plotted as 1 correctly on the graph...
However I need to display this as 0.1...
So i have created the following CDEF:
cdef=CURRENT_DATA_SOURCE,10,/
Item #1 Special Data Source: CURRENT_DATA_SOURCE
Item #2 Custom String: 10
Item #3 Operator: /
But when I do this I get the value 100 on the graphs... as if it multiplied by 100 ???
This seems very very strange ?? don't have any idea why it would do this...
Any help/info appreciated...